Construction Updates

The Davies is well under construction. To keep you informed about the work in progress, regular updates will be posted here. So, check in often to see the changes.

Update Three: August 2019

As our drone flies down into the construction site, garage level P2, concrete floor finishers are utilizing a machine known as a helicopter. This helps to stabilize the concrete and create a level surface. The final zoom shows the P3 elevator lobby taking shape along with exit stairs. Concrete formwork as well as mechanical/electrical rough-in continues.

Update Two: July 17th, 2019

The one metre deep concrete raft is nearing completion. The raft adds weight to the complex and will serve as a monolithic footing for the entire building. A drainage system and granular layer will be installed on top of the raft before we pour the slab-on-grade of the P3 parking level. Columns and walls are being formed and poured which will support the building as well as the next parking level and ramp. The next major milestone for the project is completion of the concrete formwork of the underground garage. There are additional thickened concrete transition slabs which will facilitate the custom finishes of our discerning home owners. Each of these is also considered a schedule milestone. It is projected that we will be forming the roof slab during late winter.

Update One: July 4th, 2019

The one meter deep concrete raft slab along with the elevator pits have been completed. The raft will serve as the slab-on-grade of the P3 parking level. Columns are being formed and poured which will support the suspended slab of the P2 parking deck.

inner-image-1
inner-image-2
inner-image-1
inner-image-2

June 18th, 2019